Hail Damage Spray Foam Roof & AC Replacement at Mattress Firm, 5346 Dixie Highway, Louisville, KY
The finished spray foam roof and the new rooftop AC unit at Mattress Firm, 5346 Dixie Highway, Louisville, KY.
Mr. Mike's Professional Painting completed this commercial roofing job at Mattress Firm, 5346 Dixie Highway, Louisville, KY 40216, after hail damage. We removed about 7,000 sq ft of old spray foam and installed a new spray polyurethane foam roofing system. We also replaced the hail-damaged rooftop AC unit. The work was paid for by the insurance company with our help.
Location: 5346 Dixie Highway, Louisville, KY 40216
Mattress Firm at 5346 Dixie Highway, Louisville, KY.
Before & After
These pairs show the same areas of the roof, and the same rooftop AC curb, before and after the work.
Before
After
The roof field at Mattress Firm, 5346 Dixie Highway, Louisville, KY: the old hail-damaged spray foam, then the new foam roof after the silicone coating.
Before
After
The same area around the skylight, looking toward Dixie Highway: stained old foam before the tear-off, and the finished roof with the new rooftop AC unit.
Before
After
The rooftop AC unit at Mattress Firm, 5346 Dixie Highway, Louisville, KY: the old unit on its curb, then the new unit being set in the same place with a crane.
How We Did It
We documented hail damage to the existing spray foam roof and the old rooftop AC unit, including cracks in the foam, a core sample of the old layers, and the damaged AC coil.
We tore off the old spray foam, insulation, and the modified bitumen roof underneath, and hauled the debris away.
We installed new rigid insulation and new drip edge along the roof edge.
We sprayed a new polyurethane foam roof, including around the rooftop units and along the parapet.
We took off the old rooftop AC unit and set a new commercial rooftop unit, with a curb adapter, using a crane.
We applied a silicone roof coating over the new foam, including the parapet walls.
Mid-job: the old roof torn off down to the gravel layer, with new foam and insulation along the edges.
Fresh spray polyurethane foam along the parapet, before the topcoat.
The new rooftop AC unit being lowered onto the curb adapter.
The crew spraying silicone coating on the parapet walls over the new foam roof.
Scope of Work
This is the work completed on this job, in plain words:
Tear off and haul away the old spray foam roof, insulation board, and modified bitumen roofing (about 7,000 sq ft).
Install new rigid foam insulation board.
Install a new spray polyurethane foam roof, including primer and a silicone topcoat.
Replace drip edge.
Replace the hail-damaged rooftop air conditioning unit: remove the old unit and install a new commercial rooftop unit with a curb adapter and hail guards.
Repair interior ceiling tiles where the roof work required it.